Posted by: braddenvillage | February 7, 2015

A43/A5 Tove Roundabout Traffic Management Bulletin

lafarge

A43/A5 Tove Roundabout Economy Scheme

Traffic Management Bulletin

Traffic Management for the signalisation scheme of the Roundabout and improved pedestrian facilities at the A43/A5 Junctions at Tove Roundabout which commenced on Monday 15th September 2014for approximately 22weeks duration

The scheme involves the widening and signalisation of the approaches to, and the circulatory carriageway of, the A43/A5 Tove Roundabout and installation of traffic signals and pedestrian facilities on the A43 and A5. The associated civils work includes paving, signalling, drainage, lighting, road markings, landscaping signage and fencing.

The Traffic management for the works is 24/7 narrow lanes, Northbound & Southbound of the A43, with day work on the A43 and A5 being carried out during off-peak hours.

The night shift TM works are envisaged to be Monday to Saturday (A43:-20:00 to 06:00, A5:- 20:00 to 06:00).

And occasional Sunday Day/night working.

There will be various full overnight closures at periods to be advised.

There will be various lane closures on the A43, Northbound and Southbound.

The A5 will be single lane running during off-peak times at Tove Roundabout.

Occasionally there will be two way temporary signals installed on A5 off-peak.

There will be a 50mph speed restriction in place on the A43& A5for the duration of the works.

Week Commencing 9th February 2015

Night works (20:00 to 06:00)

Monday 9th

A43 NB Lane closures

A43 SB Lane closures

A5 NB/SB 2 way traffic lights

Towcester Rd closed

Lane closures Tove Rbt

Tuesday 10th

Wednesday 11th

Thursday 12th

Friday 13th

Saturday 14th

Sunday 15th

No Works

Day works (07:00 to 18:00)

All day works carried out off road inside narrow lanes closures

3rd party works NONE

Week Commencing 16th February 2015

Night works (20:00 to 06:00)

Monday 16th

A43 NB Lane closures

A5 NB/SB single lane

Towcester Rd closed

Lane closures on Tove Rbt

A5 possible 2way traffic lights

Tuesday 17th

Wednesday 18th

Thursday 19th

A43 SB Full Closure From Jct 15a to Tove Rbt & Tove Rbt to Abthorpe Rbt,Towcester Road Closed & 3 way traffic signals on approaches to Tove Rbt For resurfacing works on Rbt,Traffic may be directed around the Rbt in the wrong direction for these works to be carried out.

Friday 20th

Saturday 21st

Sunday 22nd

No Works

Day works(07:00 to 18:00)

All day works carried out off road inside narrow lanes closures

3rd. Party Works NONE

Note: There is no Recovery Service provided for this scheme